Rosslyn Apartments - Project Update - October 2018
Starland Pacific Group are pleased to advise that L.U Simon Builders continue to make strong
progress on site with the following milestones having been achieved through Quarter 3
of 2018:
� Services works completed at Basement B3 and B2
� Structure works for the entire building have reached 50% completion
� Services rough-in have commenced up to Level 1
� Partition works commenced at Ground floor
� Tower Level 5 transfer slab formed for pouring
� Blockworks in progress at basement levels
With structural works now progressing ahead, Starland Pacific Group look forward to reporting
on significant progress for both structural and apartment fit-out works in the next
construction update.
COMPLETION:
�Construction completion at Rosslyn Apartments, West Melbourne continues to remain on
track for Quarter 2 2019, with settlement expected to follow shortly thereafter.